Capital Project 2022

Keeping up with THE LATEST PROGRESS

 

In May, 2022, voters approved a $23.2 million capital project to make critical repairs at all five schools. Since then, the district has been making steady progress toward completion.

The project was broken up into two phases. Phase one is being completed now. Phase two will be tackled soon.

Scroll down for an update on each phase.

Phase One updates

Green - COMPLETE

Blue - In-progress

Black - Complete by Summer 2024


Phase One Photos

Phase two projects

 

What’s left to be done?

These are the projects that are in critical need of repair but whose condition does not threaten the ability to open school.

These include most of the exterior site work (parking lots, etc), some heating and HVAC work, and the multi-sport athletic facility. 

The work for phase two will be completed one year behind phase one, with a target completion date of summer 2025.

Capital Project Update Presentation

 

“Our number one priority is, and has always been our students. All decisions for this project were made with them in mind”

— CCSD Board of Education